November 2022 Construction Update
The piling layout at the marina has been finalized; there will be seven pilings, each 20" in diameter.
In Palatka, Florida fabrication of the hull continues with deep frame installation and stiffeners being welded to the main deck. Barge welding, assembly, and finish coating will be ongoing over the course of the next two months. The barge is on schedule to be tugged up the coast to a Wilmington dock yard in January 2023 so the building shell construction can begin.