Marina Updates

At the Wrightsville Beach Marina, seven new, steel pilings have been placed. The temporary removal of the existing marina docks is complete, and the seven new permanent mooring pilings have been installed.  Dock reinstallation is in full swing and will be completed this week.

Exterior

The exterior, fire-rated sheathing was completed and the team is currently installing exterior siding. All rooftop mechanical equipment has been set, and the rooftop equipment screening has been installed.

Glass installation

Window glass installation is nearing completion of major punched openings.  Over the next four weeks the exterior siding and balcony deck will be the main areas of focus.

INTERIOR

Inside, the interior walls and stairwell are being framed, and the ceiling framing continues. All mechanical, electrical, plumbing, and fire suppression trades are installing their rough-in piping, testing and getting ready for drywall.